The new $7.0m Maniototo Hospital is scheduled to be completed in time for its mid-February audit. Logic have been the Project Managers on the facility from its inception. The facility will have 26 rooms comprising of rest-home residents and hospital patients. http://www.thenews.co.nz/community/new-hospital-progress-is-right-on-schedule/
Hospital on schedule
By Logic Group Healthcare Jan 28, 2019
On the home stretch!
By Logic Group Community, Healthcare Dec 09, 2018
The Maniototo Hospital new build is progressing well, with painting and floor coverings underway in the main Hospital. The access road is being prepared for asphalting and the Boiler House, Wood Chip Bunker and related services are well underway.
Maniototo Hospital
By Logic Group Healthcare Jun 19, 2018
Framing is now being erected and should be completed by 29th June. The trusses arrive on site next week. It’s looking good!
Maniototo Hospital Foundations Underway
By Logic Group Healthcare, Retirement Jun 03, 2018
The slab preparation, block laying and drainage complete. Last week we celebrated the first pour of 3. Frost protection has been addressed by laying polystyrene slabs on top of the new concrete foundations.