The new $7.0m Maniototo Hospital is scheduled to be completed in time for its mid-February audit. Logic have been the Project Managers on the facility from its inception. The facility will have 26 rooms comprising of rest-home residents and hospital patients. http://www.thenews.co.nz/community/new-hospital-progress-is-right-on-schedule/
Hospital on schedule
By Logic Group Healthcare Jan 28, 2019
On the home stretch!
By Logic Group Community, Healthcare Dec 09, 2018
The Maniototo Hospital new build is progressing well, with painting and floor coverings underway in the main Hospital. The access road is being prepared for asphalting and the Boiler House, Wood Chip Bunker and related services are well underway.
Maniototo Hospital Watertight
By Logic Group Healthcare Aug 29, 2018
The roof, and windows are now in place, with work approximately 1 week ahead of schedule. Currently the sub-trades are well into the first fix. The doors have arrived, and are being installed.
Car Park Completed
By Logic Group Healthcare Aug 12, 2018
The Mercy Hospital Car park was completed and handed over on 10th August 2018. On Saturday 11 August, at 9.30am, it was officially opened with a walk-in preview and blessing.
Maniototo Hospital
By Logic Group Healthcare Jun 19, 2018
Framing is now being erected and should be completed by 29th June. The trusses arrive on site next week. It’s looking good!
Colquhoun Lecture Theatre – Southern District Health Board
By Logic Group Business, Client, Healthcare Jun 08, 2017
Logic Group recently handed over the Colquhoun Lecture Theatre to the Southern District Health Board, after an extensive environmental clean to remove asbestos in the ceiling space, wall cavities and under croft. The theatre seats 300 and is primarily used by the University of Otago Medical School.
Dunedin Hospital MRI Lift
By Logicgroup Business, Client, Healthcare Nov 12, 2016
The 5 tonne MRI machine was lifted out of level 1 of the Clinical Services Building on Saturday 12th November. The waiting room, triage and reception of the Emergency Department were temporarily evacuated while the lift took place. The replacement MRI is due to be lifted into the same space in the next week.
Mercy Hospital Infrastructure Project
By Logicgroup Business, Client, Feasibilities, Healthcare Nov 07, 2016
Today marked the successful lift of a 4 tonne electrical transformer onto a concrete pad. A crane was needed as the site was inaccessible by any other means. The transformer is part of the new energy strategy for the Mercy Hospital site.