The project is on track at Knox College this week – Wilson bedroom joinery is being installed to the first of 4 houses and vinyl laying in the bathrooms; Glendining masked and sealed for paint before 25th December; Marshall above grid services QA completed and gib ceiling boards going up; Mackay door install, blocking and straightening continuing; and Arden house paint and flooring complete, final fit off electrical and plumbing before 25th December.