Otago Polytechnic, Level 4, Forsyth Barr House, 165 Stuart Street Dunedin 9058

Work continues on finishing the O Block extension ahead of the planned completion date next month. Window joinery and glazing installation is continuing – along the ground floor corridor it should be brighter and more pleasant with glazing going in meaning some of the construction hoardings were been removed.

Knox College, Level 4, Forsyth Barr House, 165 Stuart Street Dunedin 9058

The exterior cladding is 90% complete and we are preparing the exterior for a wash down and repaint. The scaffold dismantle is progressing and the grassed courtyard will be handed over to the landscapers this week to rejuvenate to grass again after two months of foot traffic.