Knox College Progress

By Logic Group Uncategorized Comments Off on Knox College Progress

Knox College, Level 4, Forsyth Barr House, 165 Stuart Street Dunedin 9058

The project is on track at Knox College this week – Wilson bedroom joinery is being installed to the first of 4 houses and vinyl laying in the bathrooms; Glendining masked and sealed for paint before 25th December; Marshall above grid services QA completed and gib ceiling boards going up; Mackay door install, blocking and straightening continuing; and Arden house paint and flooring complete, final fit off electrical and plumbing before 25th December.